What a reference from a trading company can honestly show
Not that we can build. That we have bought the awkward items, cleared them into a difficult country and had them standing on site when the programme said they had to be there. That part of these projects is ours to claim.
What we supplied, and where it came from
Three programmes: two running into Russia, one into Indonesia. The pattern was the same in each. The contractor needed goods that were either not made locally at a workable price or not available in the quantity the programme demanded, and we bought them abroad and brought them in.
- Structural steel and formwork, out of China. Section and plate for fabricated structures, and the formwork and shoring the monolithic work was poured against.
- Part of the inert materials, out of China. Aggregate and fill for the marine and earthwork packages.
- The machinery fleet, out of China. Cranes, excavators, loaders and site trucks, imported rather than hired. On a site a thousand kilometres from the nearest rental yard that is not a preference, it is the only version that works.
- Bridge equipment, out of the European Union. The running hardware a bridge needs to work properly, bought in Europe because the specification and the service life decided it rather than the price.
- Finishes from China, pool plant from the European Union. For the villa project on Bali, shipped into Indonesia from two continents against one fit-out programme.
Quantities, contract values and the names of the buying companies are not published here. They belong to the contractors who bought the goods. A reference can be arranged on request, with their agreement.
Russia: Sakhalin, Kamchatka, Primorye and Moscow
Marine works in the port of Kholmsk and on the Kamchatka coast, a railway bridge at Nakhodka, a resort at Artyom and listed buildings in central Moscow. Different packages on one import channel.
What makes this group worth showing is not the architecture. It is that a good part of it stands where the sea freezes, the road ends and the navigation window is counted in weeks. Goods that arrive late there do not arrive at all until the following year.






Bali: finishes and pool plant into a villa project
Sun on the Hill, a complex of six villas at Nusa Dua. The finishes came from China, the pool equipment from the European Union, both landed in Indonesia against the developer’s fit-out programme.
The three images below are the developer’s visualisations of the villas rather than photographs of finished buildings, which is why they are marked as such.



Why a trading company publishes other people’s buildings
Because the questions that decide a first order are not about catalogues. They are whether we have actually moved steel across a border, whether we know what a crane costs to land rather than to buy, and whether we have supplied a site that could not wait. These projects are the answer.
What they are not is a construction capability. We do not build. We buy, we verify, we ship and we hand over the documents, and on every site above somebody else did the building. If a quotation from us ever reads as though we are offering more than that, it is wrong and we would rather be told.
What buyers ask about these references
The four that come up as soon as the pictures load.
Did ISP Group build these objects?
No. They were built by their own contractors. Our team's part was the supply: finding the producers, buying the goods in our own name and delivering them to site. Anything past that point is somebody else's credit and we do not claim it.
Can you supply the same goods somewhere else?
Steel, formwork, plant and finishes are the same purchase wherever they land. What changes is the route and the clearance: admissibility at the destination, a broker who has cleared this product there, and a document set that has actually passed. We say how long building that takes before quoting rather than after.
Why import machinery instead of renting it?
On a remote site there is nothing to rent. Once plant has to be mobilised several thousand kilometres and held for the length of a programme, buying it abroad and importing it is usually cheaper than hiring locally, and it is always more certain.
Will you give the contract value or the buyer's name?
No. Those belong to the counterparties rather than to us, and a supplier who publishes them is telling you what he will publish about you. A reference can be arranged on request, with the buyer's agreement.
Where this turns into a price for you
The same work, described from the buying side rather than from the site.
Send a specification. Get a landed price.
Product, quantity and destination port is enough to start. If you only have a problem, describe it and we will write the specification with you.