The largest cost that never appears in a quotation
Freight is negotiated to the dollar and these are discovered on an invoice weeks later. On a lane where clearance is slow they are not an edge case, they are a line in the budget.
Which clock is which
Demurrage is charged for the container occupying space in the terminal after the free time ends. It is the port's or the carrier's charge for storage, and it runs whether or not your paperwork is ready.
Detention is charged for the container being away from the terminal, at your yard, after the free time for unpacking ends. It is the carrier's charge for its box not being back in circulation.
Some carriers merge the two into a single combined free time, which sounds generous and is usually shorter in total. Read which model the quotation uses before comparing two offers.
A third charge, port storage, can run alongside demurrage and is billed by the terminal rather than the line. On congested ports it is the larger of the two.
Free time is a negotiated number, not a fact
Free time varies by carrier, by trade lane, by season and by how much volume you give the line. It is routinely extendable at the time of booking and almost never extendable afterwards, which is the whole point: ask for it when you still have something to trade.
Reefer free time is dramatically shorter than dry, often a small fraction of it, and reefer demurrage is charged at a higher rate because the box is drawing power. On a frozen programme this is the single most expensive thing to get wrong, and it is why the clearance file has to be complete before the vessel arrives rather than after.
Why the clock usually runs
- Documents late. Originals still in the post, a telex release not yet actioned, a certificate missing a signature.
- Classification queried. Customs disagrees with the code and the entry is held while it is resolved, which is why the code is agreed before the order.
- Inspection. A physical examination adds days and is not under anyone's control; it is a budget line with a probability, not an exception.
- No haulier booked. The box is cleared and nobody arranged a truck, which happens more often than anyone admits.
- Receiving site cannot unload. No forklift for the weight, no dock, nobody on site on Friday afternoon.
- Port congestion. Not your fault and still your invoice.
Merchant haulage and carrier haulage
If the carrier arranges the inland leg, the free time and the charges sit inside its contract and it has an interest in moving the box. If you arrange your own haulier, the line's detention clock still runs and nobody on the carrier's side is watching it for you.
Neither is always cheaper. What matters is knowing which one you bought, because the two put the risk of a slow truck in completely different places.
How we keep the clock stopped
- Negotiate free time at the booking, in writing, as part of the rate rather than as a favour afterwards.
- Have the full document set with the broker before the vessel arrives, not when it berths.
- Agree the tariff classification before the order so a query is unlikely.
- Book the haulier against the estimated arrival and re-confirm when the schedule moves, which it will.
- Confirm the receiving site can take the weight and has someone there on the day.
- On reefer, treat the shorter free time as the binding constraint on the whole schedule, because it is.
Where we quote DAP, as on the Durban corridor, these risks sit with us rather than with the buyer, which is the honest reason a DAP price is higher than a port price.
Questions on this
The ones we are asked most often.
What is the difference between demurrage and detention?
Demurrage is charged while the container is still inside the terminal after free time expires. Detention is charged while the container is outside the terminal, at your premises, after the unpacking free time expires. Different clocks, often different invoices.
How much free time should I ask for?
More than the default, and ask at booking. The number depends on the lane and your volume. What matters is that it is written into the rate, because after arrival nobody extends it.
Who pays if the port is congested?
Normally the importer, which feels unfair and is how the contracts are written. The practical defences are a longer free time negotiated up front and a complete document set lodged before arrival.